Inspection stages will evidently differ, depending on the nature of a construction project. The inspection stages mandated by the Ontario Building Code are as follows:
- Footings (prior to placement of concrete)
- Lateral Sewers & Water (prior to backfill)
- Foundation
- Under Slab Drains
- Rough-In Plumbing
- Framing - All rough-in plumbing, wiring, rough-in mechanical and other services must be complete.
- Solid Fuel Burning Appliance (e.g., wood stoves, fireplaces)
- Insulation & Vapour/Air Barrier
- Fire Separations - Contact your Building Inspector for the timing of this inspection.
- Fire Protection Systems - Stand pipe, sprinkler, fire alarm and emergency lighting systems are also inspected by the Owen Sound Fire Department. Contact the Fire Prevention Office at (519) 376-2512.
- Final Plumbing
- Final Interior - You must have a water meter installed by the City to receive the 'occupancy certificate'. A list of inspection items for occupancy is available from your Building Inspector or at the Building & By-law Division office.
- Final Exterior